At first blush not much has been done since the 20-Oct posting. A fair amount of cosmetic work has been done. The granite countertops have been installed along with the sinks in the bathrooms and kitchen. All floors have been swept out in preparation …
Archives for October 2015
20-Oct-2015 Bunker Loop House
Well - today almost felt like I walked into a beehive! When I got there the foreman for the project was there so spent some time going over several questions with him. As you can see below the driveway and some of the sidewalks were poured. The …
14-19Oct-2015 Bunker Loop House
Well, am finally getting some more pictures posted. Things are proceeding on pace - not my pace but the builder's pace. During the past week they got the tile laid - floors and bath areas as well. A few days ago they got the yard graded. Brought in …
08-OCT-2015 Bunker Loop House
Last week (week of 28-Sep) they got most of the crown molding done. But nothing much else was done? This week they have started the painting. Tuesday and Wednesday were spent getting ready to paint as everything except wall, ceiling and molding had …