This entry covers the past week - I cannot see posting a picture of just a stack of concrete blocks! So anyway, last Saturday they delivered the concrete blocks to build up the foundation. Nothing was done until Tuesday when they did start laying …
Quail Creek House
19-June-2015 Bunker Loop House
Well, they did the rebar yesterday for the foundation and got the foundation poured today. …
18-June-2015 Bunker Loop House
They have now put the re-bar in the trenches in preparation for the pouring of the foundation. Today is Thursday and looks like we really do have a buyer! This is the third day she has come by to see the house. Came by Tuesday (may have been Monday) …
15-June-2015 Bunker Loop House
Finally getting something done! The major problem has been getting the permit from the City of Fairhope. It takes about 7+/- weeks to get the permit - just got it last Friday. Compare that to Daphne at three days (max) and Spanish Fort at a week or …
31-May-2015 Bunker Loop House
Nothing much done for the past couple of weeks. The pine tree on the right side of the yard was removed, a power pole was installed on the right side of the yard and a dumpster was dropped in. Keep tuned it will occur. …